30

  No. Execution Period Project Scope of Work Remarks View  
  10 2008.01 ~ 2008.05 Wonju Batch Plant - Tong Yang Major Co. Cement Plant  
  9 2007.03 ~ 2007.06 Chuncheon Batch Plant - Tong Yang Major Co. Cement Plant  
  8 2007.02 ~ 2007.05 Haman Batch Plant - Tong Yang Major Co. Cement Plant  
  7 2006.07 ~ 2006.10 Replace the cable straight joints for Oxygen Plant - B Block - Hyundai Steel Co. Steel Plant  
  6 2006.03 ~ 2006.03 Namgwangju Cement Plant - Tong Yang Major Co. Cement Plant  
  5 2006.03 ~ 2006.06 Hwhaseong Cement Plant - Tong Cement & Energy Corp. Cement Plant  
  4 2005.10 ~ 2006.02 Wolsung Nuclear Power Plant Analysis Work - Koera Hydro and Nuclear Power Co. Nuclear Power Plant  
  3 2005.02 ~ 2005.04 Kori Nuclear Power Plant C.B Replacement Work - Koera Hydro and Nuclear Power Co. Nuclear Power Plant  
  2 2004.03~2006.09 345kV Yang Yang-dong Hae Overhead Transmission Line Project (#1~2 Distrcit) - Doosan Constrction Co.,Ltd. Transmission Line  
  1 2001.07 ~ 2002.05 345kV/765kV T/L from Ul Jin Nuclear Power Plant to Tae Baek S/S - Samsung Corporation.,Ltd. Transmission Line